Project Schedules


Sabine Liquefaction Project Schedule Trains 1 – 4

July 26, 2010 – Submitted NEPA Pre-Filing Request

August 4, 2010 – Received FERC Approval to use Pre-Filing Process

January 31, 2011 – Filed NGA Section 3 Application

December 28, 2011 – Issuance of Environmental Assessment / Environmental Impact Statement

January 31, 2012 – Filed Initial Implementation Plan

April 16, 2012 – Issuance of Authorization

August 9, 2012 – Commenced Construction

February 24, 2016 – Exported First Commissioning Cargo from Train 1

May 27, 2016 – Train 1 Reached Substantial Completion

September 16, 2016 – Train 2 Reached Substantial Completion

March 31, 2017 – Train 3 Reached Substantial Completion

October 9, 2017 -- Train 4 Reached Substantial Completion


Sabine Liquefaction Expansion Project Schedule – Trains 5 & 6

February 27, 2013 – Submitted NEPA Pre-Filing Request

March 8, 2013 – Received FERC Approval to use Pre-Filing Process

September 30, 2013 – Filed NGA Section 3 Application

April 6, 2015 – Issuance of Authorization

April 13, 2015 – Filed Initial Implementation Plan

June 30, 2015 – Commenced Construction on Train 5

Q2 - 2019* – Train 5 In-Service

*dates are estimates and are subject to change

Last updated 04/25/17