Project Schedule

 

Corpus Christi Liquefaction Project Schedule

August 31, 2012 – Filed FERC Application

October 8, 2014 – Issuance of Environmental Impact Statement

December 30, 2014 – Issuance of FERC order

December 31, 2014 – File Initial Implementation Plan

May 13, 2015 – Commence Construction on Trains 1 - 2

2018* – Liquefaction Project In-Service

*dates are estimates and are subject to change

Last updated: 07/21/16
Sabine Pass Liquefaction Construction Commissioning in 2016 LNG Terminals
Annual Report Cheniere Energy’s 2016 Annual Report Recent Annual Reports
Careers Build a future with Cheniere Energy Careers
Community Relations Cheniere is proud of the role we play in the communities where we operate and live Community Relations
Safety and Environment Our constant goal 100% safe and incident free facilities Safety and Environment
Cheniere Offices Professional staff based in London, Houston, Santiago and Singapore Map
Craft Development Program Over 150 accepted and over 30 graduates employed Careers in Craft Development Program
®2017 Cheniere Energy, Inc. Copyrights - All Rights Reserved