Platform Capacity in Aggregate ~9% of Expected Global LNG Market by 2020

~4.5 mtpa Operating, ~27.0 mtpa Under Construction

Sabine Pass Terminal Corpus Christi Project

Project Schedule

June 1, 2015 – Submitted request to initiate pre-filing review process

June 9, 2015 – Issuance of FERC approval to begin pre-filing process

2016* – File FERC Application

2017* – Issuance of FERC order

2017* – Commence Construction

2021* – Liquefaction Project In-Service

*dates are estimates and are subject to change

 

Last updated 08/08/16